The Design and Build of a new Health Club adjacent to the existing hotel.
The works comprised the partial removal of the existing flank wall to the hotel and strip out and removal of the existing pool and other leisure facilities followed by the construction of Swimming Pool, Spa Pool, Sauna / Steam Room, Changing Facilities, Reception, Treatment Rooms and Aerobics / Fitness area, all enclosed in a new extension built in the same theme as the existing hotel.
Challenges
- Working in close proximity to existing hotel.
- Ground conditions.
- Working hand in hand with the Hotel Manager to minimise disruption to the residence.
Facts & Figures
Form of Contract - JCT 2005 Design and Build.
Programme - 40 Weeks.
Final Value - £2 Million